Timeline

Jan, 04, 2026

City Hearing Advances Sendero Forward

January 2026

Funding Proposal Submitted

Feb, 18, 2026

Senate Bill 151 Passes

Sol Housing provided letters of support to legislative committees, as we feel relief from construction material & labor gross receipts tax will make a significant difference in affordable housing projects being able to close finances. . SB 151 reduces the amount of gap funding we need, therefore making the development more likely to close financing and get built. On a project like Sendero, this will make an even more significant impact on the total cost of construction.

Feb, 19, 2026

Sendero ABQ Feedback Site Created

Mar, 20, 2026

Preliminary Reservation and Rejections Letters Issued

May, 20, 2026

Housing New Mexico Board Approval of 2026 LIHTC Awards

If awarded, then the proposed construction timeline will apply.

Feb, 02, 2027

Building Permits Obtained

(if awarded funding)

Mar, 10, 2027

Construction Begins

(if awarded funding)

Jan, 31, 2029

Lease-Up

(if awarded funding)

Mar, 10, 2029

Construction Completion

(if awarded funding)